Plan the approvals around the complete operation.

A renewable-gas project can involve planning, environmental protection, material handling, safety, utilities, gas delivery and product-market requirements. Map the full operation early, including co-products, so equipment and contracts reflect the activities that can lawfully proceed. [[ Environment Protection Authority Victoria, Safe production and use of digestate guidelines ](https://www.epa.vic.gov.au/safe-production-and-use-digestate-guidelines), [ NSW Environment Protection Authority, Resource recovery framework ](https://www.epa.nsw.gov.au/Your-environment/Recycling-and-reuse/resource-recovery-framework), [ Australian Energy Regulator, AER, Gas pipeline regulatory determination role ](https://www.aer.gov.au/gas-pipeline-regulatory-determination-role); C01]

Digester construction, site plans and completed plant concept
Conceptual illustration · not a project photograph or engineering design

Define the project scope once

Prepare a core description of site, feedstocks, throughput, processing, storage, traffic, utilities, emissions and intended products. Identify baseline operations and proposed changes separately. An existing facility adding recovery equipment may need variations or additional requirements assessed.

Identify each decision-maker

List the relevant authorities, network operator and certification bodies. Record the decisions required, their evidence and dependencies. Shelby recommends a coordinated approvals plan and lead contact; these are recommended working arrangements, not a currently guaranteed national single approval.

Reuse suitable evidence

Material descriptions, site plans and flow balances can support several assessments where accepted. Keep the core package versioned so a design change is reflected consistently. Separate legitimate additional requirements from repeated requests for the same evidence.

Resolve output pathways early

Gas sales depend on acceptance and delivery. Digestate and recovered CO₂ need lawful handling and intended uses. Establish these interfaces before assigning co-product revenue or purchasing equipment that assumes an unconfirmed specification.

Sequence around actual dependencies

Use pre-application discussions and parallel work where appropriate. Do not assume assessments can all finish at once: some need final designs, test results or another authority’s decision. Record commissioning requirements alongside construction permissions.

Measure progress honestly

Show enquiry, application, decision and commissioning milestones with dated evidence. A permit application is not an approval, and an approval is not a final investment decision. The practical objective is earlier clarity and fewer avoidable repetitions while retaining environmental, safety and community requirements.

Map authorities around the actual project boundary

An approval for a digester does not necessarily authorise new incoming waste, a gas connection or sale of an output. Begin with one project description and ask each responsible authority which activities and conditions apply.

Interface Questions for the relevant authority / specialist
Land use / planning Permitted use, traffic, land constraints and community process
Incoming resources Waste classification, acceptance, storage and processing permission
Water / odour / air Water supply, discharge, emissions, monitoring and management
Process safety / dangerous goods Gas, pressure, chemical storage and operating risk
Building / fire Works, emergency access, fire and safety requirements
Environmental permission Actual activities, thresholds, conditions and reporting
Gas delivery Network acceptance or transported-gas safety and interfaces
Product / metrology Gas quality, measurement and customer specification
Co-product handling Digestate reuse, CO₂ grade / storage and biochar use

Identify the state, council, site activity, material and output before assigning a regulator or timeline. Record dependencies, evidence owner, application status and unresolved conditions. This is a scoping map, not an exhaustive legal checklist or a promise of approval dates.

Shelby recommends coordinated evidence and clearer approval processes; this does not replace separate statutory decisions or weaken environmental and quality controls. Qualified planning, environmental and engineering advice is needed for the specific operation.

Frequently asked questions

Can an existing permit cover an upgrade?

Possibly, but review its conditions and the proposed activity with the relevant authority.

Does a national policy replace state planning approvals?

Do not assume that. Check the operative requirements and any specific legislative changes.

Can assessments run in parallel?

Where dependencies and authorities allow; an approvals plan should identify what can and cannot overlap.

Sources & References

  • Environment Protection Authority Victoria, Safe production and use of digestate guidelines

    Publication: 2024-01-29

    Observation period: Environmental framework and digestate guidance

    Relevant page / section: Victorian digestate production and use guidance

    Last link / title verification: 2026-10-11

    Publisher link checked; individual claims, costs and regulatory applicability still require review.

    High for published guidance; check current instruments and project conditions

  • NSW Environment Protection Authority, Resource recovery framework

    Publication: Date not verified

    Observation period: Framework and linked orders/exemptions; instrument-specific dates

    Relevant page / section: Claim-level locator not yet verified

    Last link / title verification: 2026-10-11

    Publisher link checked; individual claims, costs and regulatory applicability still require review.

    High for framework; an order applies only within its scope and conditions

  • Australian Energy Regulator, AER, Gas pipeline regulatory determination role

    Publication: Date not verified

    Observation period: Forms of pipeline regulation

    Relevant page / section: Claim-level locator not yet verified

    Last link / title verification: Not verified

    Verification incomplete, do not rely on this reference for an investment or approval decision.

    High for regulatory framework; pipeline-specific conditions and connection contracts differ

  • Shelby Bioenergy, Shelby’s National Renewable Gas Policy consultation response

    Publication: 2026-10

    Observation period: October 2026

    Relevant page / section: Supplied company position

    Last link / title verification: Not verified

    Company position / supplied material, not independent evidence.

    Proposals and scenarios, not adopted policy or market offers.